What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning
-
A
Verify that each team's uncommitted objectives have lower business value than the committed PI Objectives in order to reflect proper prioritization
-
B
Facilitate the ROAMing of each team's risks
-
C
Encourage discussion of each team's product Vision as part of the final plan review
-
D
Facilitate all teams when they are presenting their final plans to the entire Agile Release Train