FREE Professional Scrum Master Questions and Answers

0%

Who is in charge of keeping track of how much work is still left to do in each sprint to determine whether the goal will be achieved?

Correct! Wrong!

The total amount of work in the Sprint Backlog at any one time throughout a Sprint may be added up. For each Daily Scrum, the Development Team keeps track of the overall work still to be done in order to estimate the chances of completing the Sprint Goal. The Development Team may oversee its development by keeping tabs on the unfinished work throughout the Sprint.

What two characteristics are a Scrum Team need to have?

Please select 2 correct answers

Correct! Wrong!

Cross-functional and self-organizing Scrum Teams. Instead than following orders from outside the team, self-organizing teams decide how to carry out their tasks most effectively. Cross-functional teams are equipped with all the skills required to complete the task without the need for outside help.

The Scrum Master is solely concerned with the Scrum Team and typically has little interest in anybody else.

Correct! Wrong!

The Scrum Team's servant-leader is the Scrum Master. The Scrum Master aids people not on the Scrum Team in understanding which of their interactions with the Scrum Team are beneficial and which are not. To increase the value produced by the Scrum Team, the Scrum Master works with everyone to modify these interactions.

At the Sprint Planning, who is in charge of creating the Sprint Goal?

Correct! Wrong!

The Scrum Team creates a Sprint Goal after the Development Team estimates which items from the Product Backlog it will deliver during the Sprint.

Imagine the following circumstance. The Scrum Team recognized a few areas for improvement at the Sprint Restrospective meeting. What actions should the Scrum Team take? Choose the one that is best.

Correct! Wrong!

All of the work that the Development Team determines is required to complete the Sprint Goal is made accessible in the Sprint Backlog. It contains at least one high priority process improvement identified in the previous Retrospective meeting to guarantee continual improvement.

Can the Sprint Planning be completed if just the work scheduled for the sprint's initial few days is divided into units of one day or less?

Correct! Wrong!

According to the Scrum Guide, only the work scheduled for the initial days of the Sprint must be broken down at the conclusion of the planning phase, frequently into pieces of one day or fewer. The Development Team must nevertheless be able to describe to the Product Owner and Scrum Master how it plans to operate as a self-organizing team to complete the Sprint Goal and produce the anticipated increment.

How long should the sprint planning last?

Correct! Wrong!

For a one-month Sprint, Sprint Planning is time-boxed to a maximum of eight hours. It is not necessary to break out every item in the sprint backlog. Only the first several days of the Sprint are possible.