0%

What is the load hoisting sheaves minimum pitch diameter?

Correct! Wrong!

Before an operator exits the crane, he has to:

Correct! Wrong!

How many line segments are needed to lift a 36,500 lb object? load if 9,000 pounds is the highest permitted line pull?

Correct! Wrong!

An auxiliary boom point sheave, sometimes known as a rooster sheave, is used primarily to:

Correct! Wrong!

When the crane’s boom length is in between the lengths indicated in the load chart, which capacity should you use?

Correct! Wrong!

Boom length and angle can be utilized in a range diagram to ascertain

Correct! Wrong!

What minimal space between any portion of the crane or load and 850kV energized overhead power wires must be maintained, per OSHA 1926.1408?

Correct! Wrong!

When a crane operator gives two audible signals while operating the machine, what does it mean?

Correct! Wrong!

When a crane’s boom is lowered, what happens to the load’s leverage?

Correct! Wrong!

When the load moment indicator (LMI) on a crane malfunctions, what should an operator do?

Correct! Wrong!

What does the term “operating radius” mean?

Correct! Wrong!