What happens if you place timber blocking beneath a crawler crane’s track tips?
He or she plans to proceed.
Divide the hoist lines.
increases the stability of the crane
lowers the crane’s capacity
Correct!
Wrong!
Continue >>
In the context of load capacity charts, what does “jib angle to ground” mean?
The front
main boom angle less the offset of the jib
Divide the hoist lines.
only when loads are freely suspended
Correct!
Wrong!
Continue >>
When lifting with crawler cranes, which boom position would result in the most ground pressure?
Beyond the corner
Beyond the edge
Above the front
Above the back
Correct!
Wrong!
Continue >>
When can outrigger beams be covered with blocking (cribbing)?
Never
Always
Infrequently
Sometimes
Correct!
Wrong!
Continue >>
What is the rotation resistant rope’s safety factor for lifting people?
5:1
28:2
10:1
20:1
Correct!
Wrong!
Continue >>
Which accessible section of a working crane must to be blocked off all the time, according to OSHA?
From the top of the reel to the top of the drum, the rope extends.
They depend on the crane’s steadiness.
The revolving superstructure’s back swing radius
Depending on which next boom length is shorter or longer and has a lower capacity
Correct!
Wrong!
Continue >>
When operating at ground floor level close to a cellar wall, where should the outrigger pads or tracks of the crane be positioned?
At least as far back as the wall’s subsurface depth
The revolving superstructure’s back swing radius
Just far enough above the surface to release the crane weight off the tires
As long as it doesn’t produce any obvious distortion that would compromise procedures that are safe
Correct!
Wrong!
Continue >>
What is the minimal distance under $50,000 that can be kept between a crane and electrical lines?
6 ft.
15 ft.
10 ft.
20 ft.
Correct!
Wrong!
Continue >>
What is the boom hoisting sheaves’ minimum pitch diameter?
at least 20 times the diameter of the rope
at least 16 times the diameter of the rope
at least 15 times the diameter of the rope
at least 18 times the diameter of the rope
Correct!
Wrong!
Continue >>
What is the load block sheaves’ minimum pitch diameter?
at least 15 times the diameter of the rope
at least 20 times the diameter of the rope
at least 18 times the diameter of the rope
at least 16 times the diameter of the rope
Correct!
Wrong!
Continue >>
When ought one to employ a tagline?
From the top of the reel to the top of the drum, the rope extends.
The separation between the load’s center of gravity and the crane’s center of rotation
When a load’s rotation could be hazardous 1910.180(h) & 1926.1417(w)(3)(xvi) If it becomes essential, a tag or restraint line must be employed to stop the weight from rotating in a dangerous way.
Crane capacity in the gray regions above the bold lines are determined by hydraulic or structural constraints. Based on stability ratings, the crane capacity are below the bold lines.
Correct!
Wrong!
Continue >>