A homeowner entered into a contract with a builder to renovate her house for $50,000. Halfway through the project, the builder realized that due to an increase in the cost of materials, he would need an additional $10,000 to complete the job. The homeowner, under pressure to have the work finished on time, agreed to pay the additional $10,000. Upon completion, the homeowner refused to pay the extra amount. The builder sued to recover the $10,000. <br>
<br>
How should the court rule?
-
A
The builder is entitled to recover the additional $10,000 because the homeowner agreed to pay it.
-
B
The builder is not entitled to recover the additional $10,000 because there was no new consideration for the modification.
-
C
The builder is entitled to recover the additional $10,000 because the increase in material costs made performance impracticable.
-
D
The builder is not entitled to recover the additional $10,000 because the contract was already partially performed.