FREE IFMA CFM Question and Answers

0%

Bid Process Who obtains comprehensive insurance for contractors?

Correct! Wrong!

The contractor obtains comprehensive insurance for themselves. As the contractor is responsible for their own insurance coverage, they are the ones who typically secure comprehensive insurance. This ensures that they are protected against any potential damages or liabilities that may arise during the course of their work.

Traditionally, the construction contract is between the contractor and the:

Correct! Wrong!

The correct answer is "Owner." In a traditional construction contract, the contractor enters into an agreement with the owner of the project. The owner is responsible for hiring the contractor and overseeing the construction process. The architect, interior designer, and engineer may be involved in the project, but they typically work under the direction of the owner and are not parties to the construction contract.

Furniture orders that are most susceptible to time-consuming delays are usually:

Correct! Wrong!

Small orders and accessory pieces are most susceptible to time-consuming delays because they often require special handling and coordination. These orders may involve sourcing specific materials or components, which can take longer to obtain. Additionally, since these orders are typically smaller in size, they may not be given priority in terms of production and delivery. This can result in longer lead times and delays in fulfilling these orders.

During a move, if an employee does not pack according to move schedule, the person who should decide what is moved and what is discarded is:

Correct! Wrong!

The facility manager should decide what is moved and what is discarded if an employee does not pack according to the move schedule. As the person responsible for managing the facility, they have the knowledge and authority to make decisions about what items are necessary to be moved and what can be discarded. They are familiar with the needs and requirements of the facility and can ensure that only essential items are moved to the new location.

Organized project documentation is important for all of the following reasons except:

Correct! Wrong!

Organized project documentation is important for several reasons, including saving time when retrieving information, preserving credibility, and referencing all decisions. However, the reason of "occupants feeling like part of the process" is not directly related to the importance of organized project documentation. This reason focuses more on the emotional aspect of the occupants rather than the practical benefits of having organized documentation.

Leadership & Management Overview The annual report can be used to report all of the following except:

Correct! Wrong!

The annual report is a comprehensive document that provides information about the overall performance and activities of an organization. It is typically used to report financial statements, key achievements, and future plans. While it includes information about critical maintenance actions, changes in facility strategy, and the budget impact on facilities, it does not typically include project proposals. Project proposals are usually separate documents that outline specific initiatives or plans for future projects.

The most effective budgeting and scheduling technique for capital and expensed budgeted projects is:

Correct! Wrong!

Having two separate budgets and schedules for capital and expensed budgeted projects is the most effective technique. This allows for better tracking and management of expenses and resources specific to each type of project. It ensures that the budget and schedule for each project are tailored to their unique requirements and constraints, leading to more accurate planning and control. By keeping the budgets and schedules separate, it also allows for easier comparison and analysis of the performance and progress of each project individually.

Project Close-Out, Acceptance, and Commissioning The contractor submits to the facility manager the final notice of completion and asks for signature. The project is 99% complete. The facility manager should:

Correct! Wrong!

The facility manager should not sign the form until a final occupancy permit is received because this permit indicates that all necessary inspections and approvals have been obtained, and the project is officially deemed complete and safe for occupancy. Without the final occupancy permit, there may still be outstanding issues or requirements that need to be addressed before considering the project complete. Therefore, it is important to wait for the permit to ensure that all necessary steps have been taken and the project is fully finished.

Bonds What kind of bond should the contractor carry on a large project in case the contractor defaults?

Correct! Wrong!

A project-specific bid bond is the correct answer because it provides financial protection to the project owner in case the contractor defaults on their obligations. This type of bond ensures that the owner will be compensated for any losses incurred due to the contractor's failure to complete the project or meet the specified requirements. It serves as a guarantee that the contractor will fulfill their contractual obligations, and if they fail to do so, the bond amount can be used to cover the costs of completing the project or finding a new contractor.

Detailed logistics of a move for employees should be included on a(n):

Correct! Wrong!

A master schedule is a comprehensive document that outlines all the details and logistics of a move for employees. It includes information such as the timeline, tasks, resources, and responsibilities related to the move. Unlike a printout, operating procedure form, or Schedule A, a master schedule provides a holistic view of the entire move, allowing for effective planning, coordination, and execution.

To effectively operate a new building systems, all maintenance personnel should have:

Correct! Wrong!

To effectively operate a new building system, maintenance personnel need to have training in each system. This is because they need to have a thorough understanding of how each system works and what maintenance procedures are required. Without proper training, they may not be able to identify and address any issues or perform necessary maintenance tasks. Having training in each system ensures that maintenance personnel are equipped with the knowledge and skills to effectively operate and maintain the building systems.