Explanation:
Sketches should be included with the final measurements in the field books to accurately interpret non-standard measurements. Sketches provide visual representations that can clarify irregular or complex measurements, helping to ensure accurate understanding and documentation of field data.
Explanation:
The management of construction and reconstruction projects for the Department of Transportation (DOT) encompasses a range of specific responsibilities. These include planning, programming, design, contract administration, contractor payments, and overall design and contract management. Therefore, option E correctly captures all these responsibilities that are integral to managing DOT construction projects.
Explanation:
Notebooks and Estimates Procedure Manual are administrative documents, not official contract documents. Standard Specifications and Construction Manual are typically considered part of the formal contract documents that govern construction projects.
Explanation:
Supplemental Specifications are published by the Department between printings of the Standard Specifications to identify and describe changes or additions to the specifications. These documents provide updated information and modifications that are not included in the main Standard Specifications.
Explanation:
Unit Pricing and Estimates Procedure Manual is not typically considered a type of final estimates documentation. Final estimates documentation usually includes specific forms and plans directly related to the project's detailed calculations, plans, and records, such as Truck Tabulation Forms and Computer Input, Final Plans, and Computation Book Forms.
Explanation:
Procedures for running check levels and cross-sections are typically described in the Preparation & Documentation Manual (P&D M) and the Location & Survey Manual. These manuals provide guidelines and instructions for conducting surveys and verifying project dimensions, ensuring accuracy in construction projects.
Explanation:
A Computation Book is specifically used to document computations and summarize quantities in construction projects. It provides preprinted forms designed for recording detailed calculations and ensuring accurate documentation of quantities throughout the estimating process.
Explanation:
Embankment is a typical Plan Quantity Pay Item in construction projects. Plan Quantity Pay Items are items where the quantity is predetermined and specified in the project plans. Embankment refers to the quantity of earth or material used to create a raised section of ground, as detailed in the project plans. Therefore, it fits the definition of a Plan Quantity Pay Item.
Explanation:
The Preparation and Documentation Manual (PDM) is the document that sets forth the Department's methods and procedures for preparing and checking final estimates. It provides detailed guidelines and instructions on how to compile, verify, and document project costs and estimates. The PDM ensures consistency and accuracy in estimating processes across construction projects.
Explanation:
Pay items, which refer to specific tasks or materials for which payment is made in a construction project, must be summarized on a preprinted form or summary sheet. This summary ensures clarity and accountability in documenting and tracking payments related to various project tasks or materials.
Explanation:
This report is specifically used by the Paving Quality Control Technician to document quality control activities related to asphalt paving on a daily basis. It includes crucial details such as temperature measurements, asphalt mix details, and compaction efforts, ensuring that quality standards are met during the paving process.