A manager of an agile team was asked by a project sponsor to compile the lessons learnt. Which of the following statements most accurately describes this circumstance? <br>
<br>
The manager should collect the lessons learned throughout the project. <br>
The manager should collect the lessons learned only at the end of the project <br>
The manager should collect the lessons learned only when the project performance is not good <br>
The manager should collect the lessons learned only when the project performance is not good
-
A
> Since the second pH test is immediately performed after the first one, it is an extra inspection step that is not adding any value to the process. <br>
> Laboratory tests are considered quality control activities, not assurance activities. <br>
> Product release test is an in-process test (finished product is the yogurt), not a release test.
-
B
> op Down communication is the correct answer since the communication of this type needs to come from the top of the company. <br>
> Horizontal communication is used in flat organizations to communicate across the organization.
-
C
Lessons learned should be captured throughout the project when the details are fresh and team members can remember the most detail. Also this allows lessons learned early in the project to inform later phases.
-
D
> Purchasing manager is the process owner of the purchasing process. <br>
> The general manager can be the sponsor but not the process owner in this case. <br>
> The production manager & WAREHOUSE MANAGER = stakeholders and not the owner.