Explanation
A group of two or more Architects duly registered with the SEC and then with the Board of Architecture
is referred to as an architectural partnership.
Explanation
In South Africa, the United Kingdom, Ireland, Denmark, and other countries, an architectural firm is a company
that employs one or more licensed architects and performs architecture; in other countries, an architectural firm
is a corporation that provides architectural services.
Explanation
Laminated glass is a type of safety glass that may be smashed and still keep together. In the event of a break,
an interlayer between the two or more layers of glass, commonly made of polyvinyl butyral (PVB), ethylene-vinyl
acetate (EVA), or thermoplastic polyurethane (TPU), keeps it in place.
Explanation
Any pipe that links upwards from a dirt stack or vertical trash stack to a higher place to prevent pressure
variations in the stack pipe is referred to as a yoke vent. These pressure variations may obstruct drain venting.
Explanation
Shotcrete is a method of applying concrete to a vertical or above surface by projecting it at a high velocity.
The shotcrete material, which is applied pneumatically and compacted dynamically at high velocity, produces
and consolidates the concrete application.
Explanation
A notice to continue is a letter sent to a contractor by the owner or director of a corporation or firm.
The contractor will be notified of the day on which he can begin work, as specified in a previous contract.
The contract will officially begin on the date specified in the notice to proceed.
Explanation
The materials used to protect the outside of the building against moisture, thermal, and air penetration,
as well as the accompanying insulation and accessories, are referred to as Thermal and Moisture Protection.
(Doors and windows, however, are covered in Openings.) Dampproofing, waterproofing, insulation, and
roofing are all included.
Explanation
Most sign kinds, including indoor and outdoor signage, are covered under MasterFormat Division 10. Signs
that are electrical, dimensional, luminous, or navigational are all included. Also included in this category are
traffic signs and signals. Because to mobile phones and tablets, this area has gotten somewhat obfuscated
over time.
Explanation
Flooring materials are dealt with under Division 9 of a Construction Specification, however not everyone
understands how this relates to Division 3. The concrete substrate on a building project is covered by Division 3,
while the finishing, which include the flooring, are covered by Division 9.