PMP - Project Management Professional Practice Test
PMP Change Management and Control 3
An approved change request that impacts the project schedule should be reflected in which document?
Select your answer
A
The project charter
B
The schedule baseline
C
The cost management plan
D
The stakeholder register
Hint