PMP - Project Management Professional Project Scope Management Questions and Answers
A project manager is presenting a completed software module to the client for formal sign-off. The internal quality assurance team has already tested the module and confirmed that it meets all technical specifications documented in the quality management plan. Which process is the project manager currently undertaking?