1. In value engineering during construction, what is the primary goal?
Value engineering seeks to deliver all required functions at the lowest total cost while maintaining quality, safety, and performance.
2. Which quality management tool is used to distinguish the 'vital few' causes from the 'trivial many' to prioritize corrective action?
A Pareto chart applies the 80/20 rule to rank defect causes by frequency, helping teams focus on the most impactful issues first.
3. Under the CMAA Code of Ethics, which behavior best demonstrates the duty of 'loyalty' to a client?
Loyalty requires full disclosure of all material information to the client regardless of how it reflects on the CM.
4. What is the fundamental distinction between Agency Construction Management and CM at-Risk?
Agency CM serves as a professional advisor with no contractual liability for construction cost or schedule; CM at-Risk assumes financial risk by contracting with trade contractors and typically providing a GMP.
5. A project uses unit price contracts for earthwork. Actual quantities exceed bid quantities by 20%. What is the financial impact on the owner?
Unit price contracts require the owner to pay for actual quantities used at the agreed unit price, so a quantity overrun increases owner cost proportionally.
6. What does BIM stand for in the construction industry?
BIM stands for Building Information Modeling, a digital process for creating and managing comprehensive information about a construction project throughout its lifecycle.