Contract Administration Flashcards
6 cards from real CCM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 6 Contract Administration flashcards as text
What is the primary function of a construction contract?
Answer: To define legal and project terms
A construction contract is a legally binding agreement between parties, typically the owner and the contractor. Its primary function is to clearly define the scope of work, responsibilities, payment terms, timelines, quality standards, and dispute resolution mechanisms. This document protects all parties involved and serves as the foundational legal framework for the entire project.
Which of the following is typically a component of a construction contract?
Answer: Scope of work
The 'Scope of Work' is a fundamental component of a construction contract because it clearly defines all the work, materials, and services the contractor is obligated to provide. It outlines the project's boundaries, specifications, and deliverables, ensuring all parties understand what is to be built and to what standard. Without a detailed scope, ambiguity can lead to disputes and project delays.
What should a construction manager do when a change order is requested?
Answer: Document and obtain formal approval
When a change order is requested, a construction manager must meticulously document the proposed changes, including their impact on scope, cost, and schedule. It is crucial to obtain formal, written approval from all relevant parties, typically the owner, before proceeding. This process ensures legal enforceability, prevents misunderstandings, and maintains a clear record of all project modifications.
Which document tracks contractual progress and compliance during a project?
Answer: Submittal log
A submittal log is a vital project management tool used to track the status of all documents, samples, and product data submitted by the contractor for review and approval by the architect or owner. It ensures that all materials and methods comply with contract specifications before installation. This systematic tracking helps maintain contractual progress and verifies compliance throughout the project lifecycle.
What role does a 'liquidated damages' clause play in a construction contract?
Answer: Compensate for project delay
A 'liquidated damages' clause in a construction contract specifies a predetermined amount of money the contractor must pay the owner for each day the project is delayed beyond the agreed-upon completion date. This clause serves to compensate the owner for losses incurred due to project delays, without requiring them to prove actual damages in court. It provides a clear financial consequence for failing to meet the schedule.
Which party is typically responsible for issuing a notice to proceed?
Answer: Owner
The owner is typically responsible for issuing the 'Notice to Proceed' (NTP) to the contractor. This official document formally authorizes the contractor to begin work on the project. The NTP establishes the official start date of the project, from which the project schedule and contractual duration are calculated, signifying the owner's green light for construction to commence.