Cost and Time Management Flashcards
7 cards from real CCM practice questions. Tap to flip, then mark Knew It or Still Learning โ missed cards come back until you master them.
Read the first 7 Cost and Time Management flashcards as text
What does a Schedule Performance Index (SPI) of 1.15 indicate about a construction project?
Answer: The project is completing 15% more work than planned per time period
SPI = EV / PV; an SPI greater than 1.0 means the project is ahead of schedule, earning more value than planned.
A construction manager applies resource leveling to the project schedule. What is the most likely outcome?
Answer: Extended project duration or shifted activity dates
Resource leveling resolves resource over-allocations by adjusting activity start dates, which often extends the project duration.
Which document establishes the approved cost baseline for a construction project?
Answer: Cost performance baseline
The cost performance baseline is the approved, time-phased budget used to measure, monitor, and control project cost performance.
What is the primary purpose of an S-curve in construction project management?
Answer: To compare planned versus actual cumulative cost or progress over time
An S-curve plots cumulative planned value and actual cost over time, providing a visual comparison of budget versus expenditure.
A construction activity has an optimistic duration of 4 days, most likely of 7 days, and pessimistic of 16 days. What is the PERT expected duration?
Answer: 8.0 days
PERT expected duration = (O + 4M + P) / 6 = (4 + 28 + 16) / 6 = 48 / 6 = 8.0 days.
Which construction cost component typically includes site supervision, temporary utilities, and project insurance?
Answer: General conditions costs
General conditions costs cover project-wide support items such as supervision, temporary facilities, utilities, and insurance that support all work.
What is the To-Complete Performance Index (TCPI) used for in construction EVM?
Answer: To calculate the required future cost efficiency to meet the budget goal
TCPI = (BAC - EV) / (BAC - AC) and shows the cost performance efficiency required to complete remaining work within the original budget.