โ† All CCM Flashcard Decks

Cost and Time Management Flashcards

7 cards from real CCM practice questions. Tap to flip, then mark Knew It or Still Learning โ€” missed cards come back until you master them.

Read the first 7 Cost and Time Management flashcards as text
  1. What does a Schedule Performance Index (SPI) of 1.15 indicate about a construction project?

    Answer: The project is completing 15% more work than planned per time period

    SPI = EV / PV; an SPI greater than 1.0 means the project is ahead of schedule, earning more value than planned.

  2. A construction manager applies resource leveling to the project schedule. What is the most likely outcome?

    Answer: Extended project duration or shifted activity dates

    Resource leveling resolves resource over-allocations by adjusting activity start dates, which often extends the project duration.

  3. Which document establishes the approved cost baseline for a construction project?

    Answer: Cost performance baseline

    The cost performance baseline is the approved, time-phased budget used to measure, monitor, and control project cost performance.

  4. What is the primary purpose of an S-curve in construction project management?

    Answer: To compare planned versus actual cumulative cost or progress over time

    An S-curve plots cumulative planned value and actual cost over time, providing a visual comparison of budget versus expenditure.

  5. A construction activity has an optimistic duration of 4 days, most likely of 7 days, and pessimistic of 16 days. What is the PERT expected duration?

    Answer: 8.0 days

    PERT expected duration = (O + 4M + P) / 6 = (4 + 28 + 16) / 6 = 48 / 6 = 8.0 days.

  6. Which construction cost component typically includes site supervision, temporary utilities, and project insurance?

    Answer: General conditions costs

    General conditions costs cover project-wide support items such as supervision, temporary facilities, utilities, and insurance that support all work.

  7. What is the To-Complete Performance Index (TCPI) used for in construction EVM?

    Answer: To calculate the required future cost efficiency to meet the budget goal

    TCPI = (BAC - EV) / (BAC - AC) and shows the cost performance efficiency required to complete remaining work within the original budget.