Contract Administration and Management Flashcards
6 cards from real CCM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Contract Administration and Management flashcards as text
A general contractor on a public works project defaults and is terminated by the owner. Which of the following contract security instruments is specifically designed to ensure that subcontractors and material suppliers who have not been paid by the defaulting contractor receive payment?
Answer: Payment Bond
A Payment Bond is a three-party surety agreement that guarantees the contractor will pay its subcontractors, laborers, and material suppliers. If the contractor defaults on its payment obligations, the surety company will pay the valid claims, protecting these parties from loss and preventing liens against the project.
During contract closeout, which of the following milestones officially establishes the date that the owner can occupy or use the project for its intended purpose and typically marks the commencement of warranty periods?
Answer: Certificate of Substantial Completion
Substantial Completion is the contractual stage when the work is sufficiently complete for the owner to occupy and use the facility for its intended purpose. This date is critical as it usually triggers the start of warranty periods, the transfer of utilities and insurance responsibilities to the owner, and the release of most of the retainage.
A CCM is reviewing a contractor's application for payment, which includes a request for payment for custom-fabricated materials stored in an off-site warehouse. The contract allows for such payments. To protect the owner's interests before approving this payment, the CCM must FIRST verify that:
Answer: the materials are insured, properly stored, and titled to the owner.
When paying for materials not yet incorporated into the work, especially when stored off-site, the owner is taking on risk. The primary concern is to ensure the owner has legal title to the materials and is protected against loss or damage. Therefore, verifying proof of ownership, proper insurance, and secure storage earmarked for the project is the critical first step before releasing funds.
A contractor submits a shop drawing for a specified piece of equipment that deviates from the contract specifications. The design engineer reviews and rejects the submittal as non-conforming. What is the Construction Manager's most appropriate immediate action?
Answer: Direct the contractor to procure and install the equipment as specified in the contract documents.
The CCM's primary role is to administer and enforce the contract as written. Since the submittal does not conform to the contract documents and has been rejected by the designer of record, the correct action is to direct the contractor to comply with the contract requirements. Any proposed substitution must follow a formal review and approval process, but the immediate response to a non-conforming, rejected submittal is to enforce the original contract.
In construction contract administration, what is the primary characteristic that distinguishes mediation from arbitration as a method of dispute resolution?
Answer: A mediator facilitates a voluntary settlement between parties, while an arbitrator acts as a private judge and renders a decision.
The core difference lies in the role of the neutral third party and the outcome. In mediation, the mediator facilitates negotiation and helps the parties reach their own agreement but has no authority to impose a decision. In arbitration, the arbitrator hears evidence and arguments from both sides and issues a decision (an award) that is typically legally binding and enforceable.
A CCM discovers a conflict where the drawings show a specific model of light fixture, but the technical specifications call for a fixture with a higher lumen output that the drawn model does not meet. The contract's order of precedence clause states that specifications govern over drawings. The CCM should:
Answer: direct the contractor to provide a fixture that meets the performance requirements of the specifications.
The order of precedence clause is a contractual mechanism specifically designed to resolve conflicts between different contract documents. Since the clause explicitly states that specifications take precedence over drawings, the contractual requirement is clear. The CCM's role is to enforce the contract, which means directing the contractor to comply with the governing document—the specifications.