Contract Administration and Management Flashcards
6 cards from real CCM practice questions. Tap to flip, then mark Knew It or Still Learning — missed cards come back until you master them.
Read the first 6 Contract Administration and Management flashcards as text
During the execution of a construction project, the owner requests a significant change to the flooring material in a large section of the building, which was not part of the original contract. What is the most appropriate first step for the Construction Manager to take?
Answer: Document the owner's request and prepare a formal Change Order detailing the scope, cost, and schedule impacts for all parties to review and approve.
A formal Change Order is the proper contractual instrument to modify the original agreement. It must be a written document prepared for review and signature by the owner, contractor, and architect/CM, detailing the changes in scope, cost, and time. This process ensures clarity, prevents disputes, and creates a legally binding record of the modification before the work proceeds.
A contractor on a project falls significantly behind schedule due to poor management of their subcontractors. The contract includes a liquidated damages clause. Which of the following best describes the purpose of liquidated damages in this scenario?
Answer: To provide a pre-agreed, reasonable estimate of the owner's financial losses resulting from the delay.
Liquidated damages are not a penalty but a contractually agreed-upon sum that represents a reasonable forecast of the damages an owner would incur due to project delays. This avoids the difficulty and expense of proving actual damages in court.
Which of the following dispute resolution methods involves a neutral third party who facilitates discussion but does not render a binding decision, allowing the disputing parties to retain control over the outcome?
Answer: Mediation
Mediation is a voluntary and non-binding process where a neutral mediator helps the parties reach a mutually acceptable agreement. Unlike an arbitrator or a judge, the mediator does not impose a decision; their role is to facilitate communication and guide the parties toward their own resolution.
A Construction Manager is overseeing the project closeout phase. Which of the following documents is critical for formally transferring responsibility of the completed facility to the owner and is often required before the owner can legally occupy the space?
Answer: Certificate of Occupancy
The Certificate of Occupancy is a formal document issued by the local building authority or government agency that certifies a building's compliance with applicable building codes and other laws, and indicates it is in a condition suitable for occupancy. It is a crucial final step before the owner can legally use the facility.
When reviewing a contractor's monthly payment application, the Construction Manager notices that the value of stored materials claimed seems disproportionately high. What is the CM's most appropriate action?
Answer: Verify the existence, location, security, and insurance of the stored materials before approving that portion of the payment.
Proper contract administration requires verification of claims. Before approving payment for materials stored off-site or on-site, the CM has a responsibility to ensure the materials are real, properly stored and secured, insured, and designated for the project. This protects the owner's investment.
According to the CMAA (Construction Management Association of America), effective contract administration involves several key functions throughout the project lifecycle. Which of the following is a primary objective during the construction phase?
Answer: Monitoring compliance with the contract and resolving claims.
During the construction phase, a core function of contract administration is to actively monitor the contractor's performance to ensure it aligns with the contract documents. This includes managing changes, processing payments, ensuring quality and safety compliance, and proactively mitigating and resolving any claims that may arise.