CCM Cheat Sheet 2026
The 30 highest-yield CCM facts, distilled from real exam questions. Print it, save it as a PDF, or study it here — free, no sign-up.
120 questions
180 min time limit
70% to pass
- Which quality management principle does ISO 9001:2015 emphasize as the foundation for all other quality activities? → Customer focus
- A construction manager notices concrete test cylinders are consistently failing at 28 days. Which action reflects a corrective action approach? → Investigating the water-cement ratio and adjusting the mix design
- A project's Estimate at Completion (EAC) is calculated as BAC / CPI. This formula assumes: → The current cost performance will continue for the remainder of the project
- Under the CMAA Body of Knowledge, which document formally defines the quality standards and inspection procedures applicable to a construction project? → Quality Management Plan
- A contractor discovers that installed concrete has a compressive strength 15% below specification. Under a quality management system, what is the FIRST step? → Issue a nonconformance report and quarantine the affected area
- During construction, 'quality surveillance' refers to: → Ongoing observation of work activities to ensure compliance with quality requirements
- A project manager receives a cost variance (CV) of -$50,000. What does this indicate? → The project is $50,000 over budget
- A construction manager conducts a 'constructability review' during design. What is the primary cost management benefit? → It identifies construction issues early when changes are least expensive to make
- When predecessor activity B cannot start until successor activity A is 50% complete, this relationship is called: → Start-to-Start with lag
- What is the primary function of a construction contract? → To define legal and project terms
- The OSHA 300 Log must be posted in the workplace annually during which period? → February 1 – April 30
- When a project manager identifies a risk event with a 30% probability and a $200,000 potential impact, what is the expected monetary value (EMV)? → $60,000
- A construction manager uses a cost-loaded schedule to track project finances. What is the primary benefit of this approach? → It allows earned value analysis by linking costs directly to schedule activities
- A CM observes that a subcontractor is consistently installing ductwork 1/8 inch outside the specified tolerance. The CM should FIRST: → Document the observations and issue a nonconformance notice to the subcontractor
- OSHA's trenching standard requires a competent person to classify soil and inspect the excavation: → Before each shift and after any hazard-increasing event
- Which cost estimating technique uses a statistical relationship between historical data and project variables? → Parametric estimating
- Which technology captures millions of data points to produce precise 3D point clouds for as-built documentation of existing structures? → 3D laser scanning (LiDAR)
- During project execution, the actual cost of work performed (ACWP) exceeds the budgeted cost of work performed (BCWP). This indicates: → A cost overrun (negative cost variance)
- Which party is typically responsible for issuing a notice to proceed? → Owner
- Which document establishes the approved project schedule baseline against which progress is measured? → Baseline Schedule
- Which quality principle states that a relatively small number of causes typically account for the majority of quality problems? → Pareto Principle (80/20 Rule)
- What is the To-Complete Performance Index (TCPI) used for in construction EVM? → To calculate the required future cost efficiency to meet the budget goal
- The process of decomposing project deliverables into smaller, manageable components is used to create the: → Work breakdown structure (WBS)
- Under OSHA's scaffolding standard (29 CFR 1926 Subpart L), the maximum permissible deflection for a scaffold plank is: → 1/60 of the span
- In construction quality management, what distinguishes 'quality assurance' from 'quality control'? → QA is process-oriented and preventive; QC is product-oriented and detective
- In construction cost management, what is a contingency reserve used for? → Known unknowns — identified risks that may or may not occur
- Which feature is a defining element of Integrated Project Delivery (IPD)? → Multi-party agreement that aligns financial incentives of owner, designer, and contractor
- What does 'bid shopping' refer to in construction procurement, and why is it considered unethical? → Revealing a subcontractor's bid to competitors to drive down prices after award
- Which scheduling technique is BEST suited for projects with uncertain activity durations that require probability analysis? → Program Evaluation and Review Technique (PERT)
- Which method of schedule compression reduces project duration by adding resources to critical path activities? → Crashing
Turn these facts into recall:
Was this helpful?