Work order priority systems typically assign priority codes based on which two factors?
-
A
Equipment age and purchase cost
-
B
Urgency of the need and consequences of deferring the work
-
C
The skill level required and the number of technicians available
-
D
The supervisor's preference and the equipment manufacturer's recommendation