A project manager discovers a risk that was not captured in the initial risk register. What is the FIRST action to take?
-
A
Immediately escalate to the project sponsor
-
B
Document the risk in the risk register and assess it
-
C
Implement a workaround to address it
-
D
Close the risk if it has not yet occurred