Project Management Risk Management and Mitigation — Questions and Answers
Question 1: A project manager discovers a risk that was not captured in the initial risk register. What is the FIRST action to take?
- Immediately escalate to the project sponsor
- Document the risk in the risk register and assess it (Correct answer)
- Implement a workaround to address it
- Close the risk if it has not yet occurred
Correct answer: Document the risk in the risk register and assess it
Newly identified risks should be documented in the risk register and then assessed for probability and impact before any response is planned.
Question 2: Which risk response strategy is being used when a project team decides to outsource a high-risk component to a specialized vendor?
- Avoid
- Accept
- Transfer (Correct answer)
- Mitigate
Correct answer: Transfer
Transferring risk shifts the financial impact or responsibility of a risk to a third party, such as a vendor or insurer.
Question 3: What does the term 'risk appetite' refer to in project management?
- The number of risks a project can have before it is cancelled
- The amount of risk an organization is willing to accept in pursuit of its objectives (Correct answer)
- The total monetary value of all identified risks
- The frequency at which risk reviews are conducted
Correct answer: The amount of risk an organization is willing to accept in pursuit of its objectives
Risk appetite is the degree of uncertainty an organization or stakeholder is willing to accept in anticipation of a reward.
Question 4: During a risk review, a previously identified risk has its probability reduced from 'High' to 'Low' after a mitigation action was completed. What should the PM do?
- Remove the risk from the register immediately
- Update the risk register to reflect the new probability and impact scores (Correct answer)
- Escalate the change to the change control board
- Archive the risk and create a new entry
Correct answer: Update the risk register to reflect the new probability and impact scores
The risk register is a living document and should be updated whenever risk attributes change due to mitigation actions or new information.
Question 5: A project manager notices that the cost of mitigating a risk exceeds the expected monetary value (EMV) of the risk itself. What is the BEST course of action?
- Implement the mitigation anyway to follow best practices
- Accept the risk passively and plan a contingency response (Correct answer)
- Transfer the risk to a third party at any cost
- Avoid the risk by cancelling the associated work package
Correct answer: Accept the risk passively and plan a contingency response
When mitigation costs outweigh the EMV of the risk, passive acceptance with a contingency plan is the most cost-effective response.
Question 6: Which of the following BEST describes a secondary risk?
- A risk that occurs after project closure
- A risk that arises as a direct result of implementing a risk response (Correct answer)
- A risk inherited from another project
- A risk that has a secondary owner assigned
Correct answer: A risk that arises as a direct result of implementing a risk response
Secondary risks are new risks that emerge as a consequence of a planned risk response action.
Question 7: In qualitative risk analysis, a 'probability and impact matrix' is used to:
- Calculate the exact financial exposure of each risk
- Prioritize risks for further analysis or risk response planning (Correct answer)
- Assign risk owners to each identified risk
- Determine which risks require insurance coverage
Correct answer: Prioritize risks for further analysis or risk response planning
The probability and impact matrix helps teams prioritize risks by rating their likelihood and potential effect, guiding where to focus risk management efforts.
Question 8: A project sponsor asks for a single number that summarizes the overall risk exposure of the project. Which technique BEST provides this?
- Qualitative risk analysis
- Expected Monetary Value (EMV) analysis (Correct answer)
- SWOT analysis
- Risk categorization
Correct answer: Expected Monetary Value (EMV) analysis
EMV multiplies the probability of each risk by its monetary impact and sums them up to produce an overall risk exposure figure.
Question 9: Which of the following is an example of an 'opportunity' in the context of project risk management?
- A vendor delivering materials two weeks early, freeing up schedule buffer (Correct answer)
- A critical team member leaving the project
- An unexpected regulatory requirement being added
- A software tool failing during testing
Correct answer: A vendor delivering materials two weeks early, freeing up schedule buffer
In risk management, opportunities are uncertain events with positive impacts on project objectives, such as early delivery that adds schedule float.
Question 10: What is the purpose of a 'risk register' in project management?
- To formally authorize the project and assign the project manager
- To document identified risks, their characteristics, and planned responses (Correct answer)
- To track project issues that have already occurred
- To record stakeholder complaints about project risks
Correct answer: To document identified risks, their characteristics, and planned responses
The risk register is a central document that captures all identified risks, their probability, impact, owners, and planned response strategies.
Question 11: During Monte Carlo simulation for schedule risk analysis, what is the PRIMARY output?
- A list of the top ten risks by probability
- A probability distribution of possible project completion dates (Correct answer)
- A precise single completion date with no variance
- An updated project baseline schedule
Correct answer: A probability distribution of possible project completion dates
Monte Carlo simulation runs thousands of schedule scenarios to produce a probability distribution showing the likelihood of finishing by various dates.
Question 12: A project is facing a risk that the project team cannot control or mitigate. What is the MOST appropriate response strategy?
- Transfer
- Avoid
- Accept
- Escalate (Correct answer)
Correct answer: Escalate
Escalation is used when a risk is outside the project manager's authority or control and must be handled at a higher organizational level.
Question 13: Which document establishes the thresholds and processes for managing risk on a project?
- Risk register
- Risk management plan (Correct answer)
- Issue log
- Stakeholder engagement plan
Correct answer: Risk management plan
The risk management plan defines how risk management activities will be structured, including roles, methodologies, risk categories, and thresholds.
Question 14: A construction project is delayed because flooding damaged the site—an event that was identified but accepted. What is the PM's FIRST step now that the risk has occurred?
- Update the probability in the risk register to 100%
- Execute the planned contingency response (Correct answer)
- Perform a new qualitative risk analysis
- File an insurance claim before taking any project action
Correct answer: Execute the planned contingency response
When an accepted risk event occurs, the project manager should immediately execute the pre-planned contingency response to minimize impact.
Question 15: Which of the following is a key difference between a 'risk' and an 'issue' in project management?
- A risk has already occurred; an issue has not yet happened
- An issue has already occurred; a risk is an uncertain future event (Correct answer)
- A risk always has a negative impact; an issue can be positive
- An issue is tracked in the risk register; a risk is tracked in the issue log
Correct answer: An issue has already occurred; a risk is an uncertain future event
A risk is an uncertain future event that may affect project objectives, while an issue is a problem or situation that has already occurred.
Question 16: What type of risk analysis uses techniques such as decision tree analysis and sensitivity analysis?
- Qualitative risk analysis
- Quantitative risk analysis (Correct answer)
- Residual risk analysis
- Root cause analysis
Correct answer: Quantitative risk analysis
Quantitative risk analysis uses numerical techniques like decision trees and sensitivity analysis to estimate the effect of risks on project objectives.
Question 17: A project manager learns that a competitor plans to release a similar product two months before her project's launch. From a risk management perspective, this is BEST classified as:
- An internal risk
- An external risk (Correct answer)
- A technical risk
- A residual risk
Correct answer: An external risk
External risks originate outside the project and organization, such as market competition, regulatory changes, or economic shifts.
Question 18: When using the 'exploit' strategy in risk response planning, the project manager is:
- Transferring a negative risk to a third party
- Taking action to ensure a positive risk opportunity definitely occurs (Correct answer)
- Accepting a threat and monitoring it passively
- Reducing the likelihood of a negative risk event
Correct answer: Taking action to ensure a positive risk opportunity definitely occurs
Exploit is a response strategy for opportunities that seeks to eliminate uncertainty by making sure the positive event actually happens.
Question 19: A project manager sets aside $50,000 to handle identified risks and $20,000 for unknown risks. What are these reserves called, respectively?
- Management reserve and contingency reserve
- Contingency reserve and management reserve (Correct answer)
- Risk budget and contingency fund
- Operational reserve and risk allowance
Correct answer: Contingency reserve and management reserve
Contingency reserves address identified known-unknown risks, while management reserves are for unknown-unknown risks that were not anticipated.
Question 20: Which risk identification technique involves gathering a group of subject matter experts to brainstorm risks without judgment or criticism?
- Delphi technique
- Brainstorming (Correct answer)
- Nominal group technique
- Affinity diagrams
Correct answer: Brainstorming
Brainstorming brings together SMEs to freely generate risk ideas in an open, non-judgmental environment to maximize the number of risks identified.
Question 21: A tornado watch is issued for the area where a project's outdoor event is being held. The project team has no contingency plan for this scenario. What type of planning failure does this represent?
- Failure to perform quantitative risk analysis
- Failure to identify and plan for a foreseeable risk (Correct answer)
- Failure to create a risk management plan
- Failure to execute the risk response plan
Correct answer: Failure to identify and plan for a foreseeable risk
A tornado watch in a weather-prone region is a foreseeable risk that should have been identified and addressed with a contingency plan during risk planning.
A project manager discovers a risk that was not captured in the initial risk register.
What is the FIRST action to take?
What Practice Test Geeks adds beyond an AI chat for Project Management
An AI chatbot can quiz you, but it can't reproduce the exam conditions or keep your record. Here you get:
- A timed, full-length Project Management mock exam — 180 questions in 230 minutes with a 61% pass mark, modeled on the official exam's question count and time limit, followed by a score report broken down by exam domain.
- A fixed Project Management question bank: the same test every attempt, so your score is comparable from one try to the next instead of changing with every regenerated quiz.
- Progress saved on your device: completed tests, scores and missed questions stay in My Progress, so you can retake only what you got wrong.
- A printable Project Management cheat sheet you can print or save as a PDF.
- Project Management flashcards built from the same question bank.
These practice questions were written with AI tools. They are not real exam questions. We have not yet matched this exam's facts to an official source, so confirm fees, dates and rules with the exam body. Not reviewed by a subject-matter expert. Editorial policy