Which technique is most effective for managing stakeholders with high power and high interest in the program?
-
A
Monitor only
-
B
Manage closely with frequent, detailed communication and involvement in key decisions
-
C
Keep informed with periodic updates only
-
D
Minimal engagement to avoid overload