What is the primary purpose of a Program Governance Board in the PgMP framework?
Select your answer
A
To manage day-to-day project tasks
B
To provide oversight, decision-making authority, and strategic alignment for the program
C
To replace the program manager in planning activities
D
To handle stakeholder complaints