A project manager notices that a key stakeholder has shifted from 'supportive' to 'resistant' after a recent scope change. What should the PM do FIRST?
-
A
Escalate the issue to the project sponsor
-
B
Schedule a meeting to understand the stakeholder's concerns
-
C
Remove the stakeholder from the communication plan
-
D
Proceed with the project and document the resistance