PMP - Project Management Professional Practice Test

โ–ถ

PMP Managing Budget and Costs 4

Free ยท Instant Results

A project is 40% complete, has spent $80,000, and was planned to spend $70,000 for work completed. The BAC is $150,000. What is the Estimate to Complete (ETC) using the formula EAC = AC + (BAC - EV)?
โ–ถ Start Practice Test