Practice Test Geeks home

PMP Managing Budget and Costs 4

A project is 40% complete, has spent $80,000, and was planned to spend $70,000 for work completed.
The BAC is $150,000.

What is the Estimate to Complete (ETC) using the formula EAC = AC + (BAC - EV)?

Select your answer