A project manager discovers that a critical deliverable will be delayed due to an unexpected technical issue. What should the project manager do FIRST?
-
A
Notify the project sponsor immediately
-
B
Assess the impact on the project schedule and other deliverables
-
C
Request additional resources from the resource manager
-
D
Issue a change request to extend the project deadline