PMI-RMP Practice Test
Updated October 2026Facts verified Oct 28, 2026 against Project Management Institute
What the PMI-RMP is and how it works
According to Project Management Institute, “The PMI-RMP certification examination is comprised of 115 multiple-choice and multiple answer select questions. Of the 115 questions, 15 are considered pretest questions.”[1]
The PMI-RMP (Risk Management Professional) is awarded by the Project Management Institute. It is aimed at people who identify, analyse and respond to risk on projects, and it tests how you apply risk practices to situations rather than how well you recall definitions.
The exam has 115 questions, in multiple-choice and multiple-answer formats. Of those, 100 are scored and 15 are unscored pretest questions. You will not be told which ones are the pretest items, so treat every question as if it counts.
You can sit the exam at a Pearson VUE test center, which PMI recommends, or online with a proctor through OnVUE. Once you are eligible, you can schedule year-round, on demand, within your 1-year eligibility period.
If you do not pass, you may take the exam up to 3 times within that 1-year eligibility period. After 3 attempts, you must wait 1 year from the date of your last attempt before you reapply.
Once certified, you keep the credential by earning 30 PDUs in each 3-year cycle.
Eligibility requirements, application steps, fees and the exact time allowed are set by PMI and can change, and we have not listed them here. Check the official PMI-RMP page and the current exam outline before you apply.
- The PMI-RMP exam has 115 multiple-choice and multiple-answer-select questions; 100 are scored and 15 are unscored pretest questions.[1]
- PMI-RMP candidates may take the exam up to three times within their one-year eligibility period, and after three failed attempts they must wait one year before reapplying.[1]
- The PMI-RMP certification runs on a 3-year cycle, and holders renew it by earning PDUs during that cycle.[2]
- To keep the PMI-RMP certification, holders must earn 30 professional development units (PDUs) in each 3-year cycle.[2]
- The PMI-RMP exam is given at Pearson VUE test centers or securely online through Pearson VUE's OnVUE remote proctoring, in English, Arabic and Simplified Chinese.[2]
Numbers in brackets link to the official sources listed under Sources & last verified. Dates that have passed are removed automatically.
PMI-RMP Exam at a Glance
| Item | Detail | Source · Verified |
|---|---|---|
| Number of questions | 115 questions (100 scored + 15 unscored pretest)[1] | Project Management Institute · Oct 26, 2026 |
| Retake policy | Up to 3 attempts in a 1-year eligibility period; then wait 1 year[1] | Project Management Institute · Oct 26, 2026 |
| Validity | 3-year certification cycle[2] | Project Management Institute · Oct 26, 2026 |
| Renewal | 30 PDUs every 3-year cycle[2] | Project Management Institute · Oct 26, 2026 |
| Delivery | Pearson VUE test center or online proctored (OnVUE)[2] | Project Management Institute · Oct 26, 2026 |
| Testing window | Year-round on demand within a 1-year eligibility period[1] | Project Management Institute · Oct 26, 2026 |
PMI-RMP content outline and where to practise each area
The content areas below are copied from the official PMI-RMP content outline published by Project Management Institute, with the share of the exam each area carries. The right-hand column shows which of our practice sets covers it.
| Official content area | Weight | Practice on this site |
|---|---|---|
| Risk Strategy and Planning[3] | 22% | PMI-RMP Plan Risk Management Practise how a risk management plan is set up, including roles, risk appetite and tolerance, and how the approach is tailored to the project. |
| Risk Identification[3] | 23% | PMI-RMP Risk Identification Tools Practise choosing the right technique to find risks and recording them clearly in the risk register. |
| Risk Analysis[3] | 23% | PMI-RMP Qualitative Risk Analysis Practise telling qualitative from quantitative methods, and judging which risks to prioritise and why. |
| Risk Response[3] | 13% | PMI-RMP Threat Response Strategies Practise matching a threat or opportunity to the right response strategy and knowing what each strategy does and does not involve. |
| Monitor and Close Risks[3] | 19% | PMI-RMP Monitor and Control Risks Practise reviewing risk status, checking whether responses worked, and deciding when a risk can be closed. |
PMI-RMP Practice Test Questions
Prepare for the PMI-RMP - PMI Risk Management Professional exam with our free practice test modules. Each quiz covers key topics to help you pass on your first try.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Mock Test covering - PMI Risk Management Professional Implement Risk Responses. Online PMI-RMP Test practice with instant feedback.
PMI-RMP - PMI Risk Management Professional...
Free PMI-RMP Quiz on - PMI Risk Management Professional Monitor and Control Risks. PMI-RMP Exam prep questions with detailed explanations.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Practice Questions for - PMI Risk Management Professional Opportunity Response Strategies. Build confidence for your PMI-RMP certification exam.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Test Online for - PMI Risk Management Professional Plan Risk Management. Free practice with instant results and feedback.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Study Material on - PMI Risk Management Professional Qualitative Risk Analysis. Prepare effectively with real exam-style questions.
PMI-RMP - PMI Risk Management Professional...
Free PMI-RMP Test covering - PMI Risk Management Professional Quantitative Risk Analysis. Practice and track your PMI-RMP exam readiness.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Exam Questions covering - PMI Risk Management Professional Risk Identification Tools. Master PMI-RMP Test concepts for certification prep.
PMI-RMP - PMI Risk Management Professional...
Free PMI-RMP Practice Test featuring - PMI Risk Management Professional Risk Management Framework. Improve your PMI-RMP Exam score with mock test prep.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Mock Exam on - PMI Risk Management Professional Stakeholder Engagement. PMI-RMP Study Guide questions to pass on your first try.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Test Prep for - PMI Risk Management Professional The Risk Register. Practice PMI-RMP Quiz questions and boost your score.
PMI-RMP - PMI Risk Management Professional...
PMI-RMP Questions and Answers on - PMI Risk Management Professional Threat Response Strategies. Free PMI-RMP practice for exam readiness.
PMI-RMP PMI - RMP Practice Test
PMI-RMP Mock Test covering PMI - RMP Practice Test. Online PMI-RMP Test practice with instant feedback.
PMI-RMP Risk Appetite and Tolerance
PMI-RMP Test Online for Risk Appetite and Tolerance. Free practice with instant results and feedback.
Worked examples: how to reason through PMI-RMP questions
These are practice questions written for this site, not questions from the real exam. Each explanation shows why the right answer is right and why the others are wrong.
Example 1
Question: A risk manager is facilitating a periodic review to examine and document the effectiveness of the risk response planning and the performance of the risk owners in executing their assigned responsibilities. What is this activity called?
- Risk Reassessment
- Variance Analysis
- Risk Audit
- Status Meeting
Answer: C. Risk Audit
Explanation:
The answer is Risk Audit. A risk audit is a formal check of how well the risk management process is working, including whether planned responses are effective and whether risk owners are doing what they agreed to do. The question describes a review of the process and the people carrying it out, which is the audit.
Risk Reassessment looks again at individual risks, such as their probability and impact, not at how well the process is run. Variance Analysis compares planned results with actual results for things like cost and schedule. A Status Meeting is a routine update and does not examine and document effectiveness in a formal way.
Rule to remember: reassessment looks at the risks, while an audit looks at the process and its performance.
Example 2
Question: After analysis, a team decides to take no proactive action on a minor opportunity but will pursue it if it arises. This best illustrates which strategy?
- Enhance
- Exploit
- Accept
- Escalate
Answer: C. Accept
Explanation:
The answer is Accept. The team takes no proactive action on a minor opportunity and will take it if it happens. That is acceptance applied to an opportunity: you acknowledge it and do nothing to pursue it.
Enhance is wrong because it means acting to raise the probability or impact of the opportunity, and this team is doing nothing. Exploit is wrong because it means making sure the opportunity happens, which is the strongest and most active response. Escalate is wrong because it passes the matter to someone with the authority to handle it, usually when it falls outside the project's scope, and nothing is being passed on here.
Rule to remember: if the wording is no proactive action, think Accept. If the wording is doing something to make it more likely or certain, think Enhance or Exploit.
Example 3
Question: When a project team establishes a contingency reserve but takes no proactive action against a low-priority threat, which strategy is being used?
- Active acceptance
- Passive acceptance
- Avoid
- Mitigate
Answer: A. Active acceptance
Explanation:
The answer is Active acceptance. The team takes no step to change the plan for the low-priority threat, but it does set aside a contingency reserve in case the threat occurs. Setting aside that reserve is the active part.
Passive acceptance is wrong because it means doing nothing at all and not preparing any reserve; the team here has prepared one. Avoid is wrong because it changes the plan to remove the threat, and the plan is not being changed. Mitigate is wrong because it takes action to reduce the probability or impact of the threat before it occurs, which is not happening here.
Rule to remember: both kinds of acceptance leave the plan alone. Passive means nothing is prepared, while active means you have prepared a reserve or a fallback.
How to use these practice tests
Start with the official PMI-RMP exam outline and read the list of content areas. It tells you what PMI says the exam covers, and it is the source to trust over any third-party summary, including this page.
Next, take the PMI-RMP practice test or the full practice test once, without notes, to see where you are weak. Do not worry about the score at this stage. Write down every question you missed or guessed, and note the reason: you did not know the term, you misread the question, or you confused two similar strategies.
- Work through the topic sets that match your weak areas, such as The Risk Register, Quantitative Risk Analysis and Stakeholder Engagement.
- After each set, read the explanation for every question, including the ones you got right.
- Return to the official material for any topic where you keep making the same mistake.
Close to test day, take the full practice test again under quiet, uninterrupted conditions. Our questions are written by us and are not real exam questions, so use them to build judgment rather than to predict what you will see.


📝 How many questions are on the PMI-RMP exam?
The PMI-RMP exam has 115 multiple-choice questions and a time limit of 150 minutes (2.5 hours). Of those 115 questions, 15 are unscored pretest items placed randomly, so only 100 count toward your result.
START PMI-RMP PRACTICE TEST📊 What domains does the PMI-RMP exam cover?
The PMI-RMP Exam Content Outline has five domains: Risk Strategy and Planning (22%), Risk Identification (23%), Risk Analysis (23%), Risk Response (13%), and Monitor and Close Risks (19%). Identification and analysis together make up almost half of the exam.
START PMI-RMP PRACTICE TEST🎓 What are the PMI-RMP eligibility requirements?
With a four-year degree you need 24 months of project risk management experience in the last 5 years plus 30 contact hours of risk education. With a high school diploma or associate degree you need 36 months of risk experience and 40 contact hours.
START PMI-RMP PRACTICE TEST💵 How much does the PMI-RMP exam cost?
The PMI-RMP exam fee is $520 for PMI members and $670 for non-members. Because the member discount is $150, many candidates join PMI before applying, but compare it against the current membership dues first.
START PMI-RMP PRACTICE TEST🛡️ What are the five threat response strategies in PMI-RMP?
PMI lists five strategies for negative risks: escalate, avoid, transfer, mitigate, and accept. Transfer shifts ownership to a third party (for example insurance or a fixed-price contract), while mitigate reduces the probability or impact of the threat.
START PMI-RMP PRACTICE TEST🚀 What are the opportunity response strategies for positive risks?
The five opportunity strategies are escalate, exploit, share, enhance, and accept. Exploit tries to make the opportunity certain to happen, share gives part of the ownership to a partner best able to capture it, and enhance raises its probability or impact.
START PMI-RMP PRACTICE TEST🧮 How do you calculate expected monetary value (EMV)?
EMV equals probability multiplied by impact. A threat with a 30% probability and a $50,000 cost impact has an EMV of -$15,000, and an opportunity with a 20% probability of saving $10,000 has an EMV of +$2,000. Summing EMVs is the basis of decision tree analysis.
START PMI-RMP PRACTICE TEST🎯 What is the difference between qualitative and quantitative risk analysis?
Qualitative risk analysis prioritizes individual risks by rating their probability and impact, often on a probability and impact matrix. Quantitative analysis numerically models the combined effect of risks on project objectives, using techniques such as Monte Carlo simulation, decision trees, and sensitivity (tornado) analysis.
START PMI-RMP PRACTICE TEST📒 What goes in a risk register?
The risk register records each identified individual risk, typically with its description, risk owner, probability and impact ratings, priority, and planned responses. It is created during risk identification and updated throughout the project as risks are analyzed, responded to, and closed.
START PMI-RMP PRACTICE TEST💰 What is the difference between contingency reserve and management reserve?
Contingency reserve is budget or time set aside for identified risks (known-unknowns) and is part of the cost baseline. Management reserve covers unidentified risks (unknown-unknowns), sits outside the cost baseline, and normally needs management approval to use.
START PMI-RMP PRACTICE TESTPMI-RMP FAQ
Sources & last verified
- Project Management Institute — number of questions, retake policy, testing window (official source). “The PMI-RMP certification examination is comprised of 115 multiple-choice and multiple answer select questions. Of the 115 questions, 15 are considered pretest questions.” Verified Oct 26, 2026.
- Project Management Institute — validity, renewal, delivery (official source). “PMI-RMP holders need to earn 30 professional development units (PDUs) in each 3-year cycle to maintain certification.” Verified Oct 26, 2026.
- Project Management Institute — other (official source). “risk strategy and planning 22%” Verified Oct 28, 2026.
How we verify: editorial & fact-checking policy. Report an error: contact us.
How this page was made: written with AI tools and published by Nathan Beja, founder of Practice Test Geeks, who is responsible for its content. Exam facts are checked against the official sources listed below. Not reviewed by a subject-matter expert. Editorial policy
Sources & references
Exam facts on this page (fees, format, dates, passing scores) are checked against these official sources; the date is our last check. Editorial policy
- pmi.org — Exam format, retake policy, test dates, test delivery, renewal, score validity, exam information · verified Oct 2026