A project manager for a highly innovative and unprecedented technology project needs to identify potential risks.
Since there is no historical data and the team members' opinions are strongly influenced by a few dominant personalities, the project manager wants to gather expert judgment anonymously to avoid bias.
Which risk identification tool is MOST appropriate for this situation?