PMI-RMP Risk Communication and Reporting 1 — Questions and Answers
Question 1: What is the primary purpose of a risk report in a PMI-RMP context?
- To document project costs
- To communicate the overall risk exposure and status to stakeholders (Correct answer)
- To assign blame for risk events
- To replace the project status report
Correct answer: To communicate the overall risk exposure and status to stakeholders
A risk report summarizes the overall project risk exposure and individual risk status, keeping stakeholders informed so they can make sound decisions.
Question 2: Which communication artifact best captures the current risk threshold and escalation criteria agreed upon by the team and sponsor?
- Risk register
- Risk management plan (Correct answer)
- Issue log
- Stakeholder register
Correct answer: Risk management plan
The risk management plan documents agreed-upon thresholds, escalation paths, and communication roles for the project.
Question 3: A risk manager wants to present probability-impact information visually to sponsors. Which tool is most appropriate?
- Pareto chart
- Probability and Impact Matrix (Correct answer)
- Gantt chart
- RACI matrix
Correct answer: Probability and Impact Matrix
The Probability and Impact Matrix visually maps each risk by likelihood and consequence, making it ideal for executive communication.
Question 4: How frequently should risk reports typically be issued on a project?
- Only at project initiation
- Only when a risk occurs
- At intervals defined in the risk management plan (Correct answer)
- Annually, regardless of project duration
Correct answer: At intervals defined in the risk management plan
The risk management plan defines reporting cadence, which should align with the project's reporting cycle and stakeholder needs.
Question 5: A project team identifies a new high-impact risk mid-project. Who should be notified first according to best practice?
- The project sponsor and key stakeholders per the escalation path (Correct answer)
- The vendor
- The customer's legal team
- The project team only
Correct answer: The project sponsor and key stakeholders per the escalation path
High-impact risks that exceed thresholds must be escalated promptly to the sponsor and stakeholders as defined in the risk management plan.
Question 6: What is the role of a risk owner in risk communication?
- To eliminate all project risks
- To be responsible for monitoring the risk and reporting its status (Correct answer)
- To approve the project budget
- To write the project charter
Correct answer: To be responsible for monitoring the risk and reporting its status
The risk owner is accountable for tracking their assigned risk and reporting updates to the risk manager and relevant stakeholders.
What is the primary purpose of a risk report in a PMI-RMP context?