You discover mid-project that a key assumption was incorrect. What is the most effective response?
-
A
Continue as planned since changing course will cause delays
-
B
Acknowledge the error, reassess the plan, and adjust accordingly
-
C
Blame the team member who made the assumption
-
D
Report the error only after the project is completed