A facility wants to improve maintenance effectiveness. Which sequence represents the correct order of the planning and scheduling process?
-
A
Schedule → Plan → Execute → Review
-
B
Identify need → Plan → Schedule → Execute → Review/close
-
C
Execute → Plan → Schedule → Identify need → Review
-
D
Plan → Identify need → Execute → Schedule → Review