A project team is experiencing frequent requirement changes after baseline approval. What is the MOST likely root cause?
-
A
The development team is changing requirements without authorization
-
B
Requirements were not sufficiently validated with stakeholders before baselining
-
C
The project sponsor changed the business strategy after sign-off
-
D
The BA used too many elicitation techniques during discovery