A change agent notices that a senior leader verbally endorses the initiative in meetings but consistently misses milestone reviews. Which engagement strategy best addresses this pattern?
-
A
Escalate the absences to the project sponsor
-
B
Schedule a private conversation to surface barriers to active participation
-
C
Proceed without the leader's involvement to avoid conflict
-
D
Redistribute the leader's responsibilities to engaged stakeholders