How does a change impact assessment fundamentally differ from a change risk assessment?
-
A
A change impact assessment focuses on what could go wrong, while a risk assessment focuses on potential benefits
-
B
A change impact assessment evaluates the effects of change on people and processes, while a risk assessment evaluates the probability and consequences of potential problems during implementation
-
C
A change impact assessment is conducted after implementation; a risk assessment is conducted before
-
D
There is no meaningful difference — the two assessments are interchangeable