A stakeholder suddenly escalates a concern directly to the project sponsor, bypassing the PM. The BEST response from the PM is to:
-
A
Reprimand the stakeholder publicly
-
B
Acknowledge the concern, investigate it, and update both the stakeholder and sponsor
-
C
Ask the sponsor to ignore the escalation
-
D
Document it as a risk and take no further action