A project is experiencing scope creep largely driven by one influential stakeholder continuously adding requirements. The BEST response is to:
-
A
Accept all changes to maintain the relationship
-
B
Implement a formal change control process and communicate it to all stakeholders
-
C
Ignore the requests until project closure
-
D
Escalate the stakeholder to HR