A project manager discovers that a risk response is not working as planned after implementation. The BEST next step is to:
-
A
Ignore it because the response was already approved
-
B
Update the risk register and develop an alternative response
-
C
Immediately escalate to the project sponsor
-
D
Accept the risk passively going forward