Which of the following is a key difference between a 'risk' and an 'issue' in project management?
-
A
A risk has already occurred; an issue has not yet happened
-
B
An issue has already occurred; a risk is an uncertain future event
-
C
A risk always has a negative impact; an issue can be positive
-
D
An issue is tracked in the risk register; a risk is tracked in the issue log