A project manager discovers that a vendor has delivered a feature that was not in the approved scope but is potentially useful. What should the PM do?
-
A
Accept it since it adds value
-
B
Reject it and initiate a change request if the team wants it included
-
C
Include it in the project scope baseline immediately
-
D
Escalate to the project sponsor for approval without a change request