A project manager is creating a Requirements Traceability Matrix. What is its PRIMARY purpose?
-
A
Tracking the cost of each requirement
-
B
Linking requirements to their origin and tracing them through the project lifecycle
-
C
Assigning requirements to team members
-
D
Prioritizing requirements by business value