A project's To-Complete Performance Index (TCPI) is 1.15. What does this mean?
-
A
The project needs to spend $1.15 for every $1 of remaining work
-
B
The project must perform at $1.15 worth of work for every $1 remaining in the budget
-
C
The project is 15% ahead of schedule
-
D
The project has 15% of its budget remaining