When needed resources cannot be obtained internally during the Acquire Resources process, the most appropriate next step is to:
-
A
Reduce project scope to fit available internal resources
-
B
Continue negotiating indefinitely with functional managers
-
C
Procure resources externally through contracting or outsourcing
-
D
Formally escalate to the project sponsor to cancel the project