A project's EAC using the formula EAC = AC + (BAC - EV) / CPI assumes:
-
A
Future work will be performed at the budgeted rate
-
B
Future work will continue at the current CPI
-
C
The remaining budget is fixed at BAC - AC
-
D
The project will use the SPI to recover schedule