A project's SPI is 0.72 and the deadline is fixed. What action is most aligned with EVM principles?
-
A
Analyze critical path activities and consider crashing or fast-tracking
-
B
Increase the budget to compensate for schedule slippage
-
C
Recalculate PV to match current EV
-
D
Report the SPI as acceptable since it exceeds 0.5