What is the primary purpose of performing a 'forward pass' and 'backward pass' in CPM network analysis?
-
A
To calculate the cost of each activity in both directions
-
B
To determine the early and late start/finish dates and calculate float for each activity
-
C
To identify resource requirements during project execution
-
D
To validate that the network diagram has no circular dependencies