A project manager uses 'fast tracking' to compress the schedule. What is the primary risk introduced?
-
A
Increased project cost due to overtime pay
-
B
Rework and quality issues from overlapping activities that were meant to be sequential
-
C
Resource conflicts across all project phases
-
D
Loss of the original critical path