In CPM, what does 'free float' (free slack) represent?
-
A
The amount of time an activity can be delayed without delaying the project end date
-
B
The amount of time an activity can be delayed without delaying any successor activity's early start
-
C
The difference between an activity's late finish and early finish
-
D
The total time available in the project schedule buffer