A team is struggling with scope creep in an agile project. Which practice most directly helps control this?
-
A
Increasing sprint length to accommodate more features
-
B
Having a strong Product Owner who controls backlog additions and prioritization
-
C
Removing the sprint review ceremony
-
D
Allowing all stakeholders to add items directly to the sprint