A program manager must report program health to executives. Which reporting approach is MOST appropriate?
-
A
Detailed technical status reports from each project
-
B
A consolidated dashboard showing benefits, risks, and milestones
-
C
Individual project earned value reports
-
D
Weekly team meeting minutes