A program is behind schedule and the sponsor wants to compress the timeline. Which approach should the program manager evaluate FIRST?
-
A
Fast-tracking interdependent project phases
-
B
Adding more resources to all component projects
-
C
Crashing the critical path activities
-
D
Reducing program scope